This browser is not actively supported anymore. For the best passle experience, we strongly recommend you upgrade your browser.

NEWS & INSIGHTS

Our lawyers are experts in their fields. Through commentary and analysis, we give you insight into the pressures impacting business today.

| 2 minutes read

Adjudication Alert: To enforce or not to enforce– usually yes but sometimes no!

To kick off our new Adjudication Alert series, I have reviewed the recent case of Downs Road Development LLP v Laxmanbhai Construction (UK) Ltd [2021] EWHC 2441 (TCC) - a classic case of a party not liking an adjudicator's decision and looking for reasons to resist having to pay out.

The project was a residential development in Hackney for seventy nine units. There was a dispute about the sum due for an interim application and an adjudication followed. 

After weighing it all up, the adjudicator decided that Downs Road had to pay Laxmanbhai the sum of £103,836.98.

Downs Road were pretty annoyed about this. Their view was that Laxmanbhai had constructed some of the basement units so that there was less natural light than anticipated ("the capping beam claim") which would cause Downs Road future losses.  It is not difficult to see how constructing a basement unit with limited natural light is less than ideal and could affect the rent that could be charged for such units  – even if they are in a trendy part of town. Downs Road had calculated that its likely losses were £149,692 and considered that this was a defence relevant to the adjudication dispute meaning that Laxmanbhai were not entitled to anything.

The merits of the capping beam claim were not looked at as when this argument was advanced by Downs Road. Laxmanbhai claimed that the adjudicator did not have jurisdiction to take account of this defence. Taking a narrow view of jurisdiction, the adjudicator had agreed with Laxmanbhai and as such, deliberately decided to ignore it.                                                                                                       

Downs Road commenced proceedings to challenge the enforceability of the decision arguing that ignoring the capping beam claim amounted to a breach of natural justice. The court agreed with Downs Road confirming that a deliberate failure to address a material issue which was before the adjudicator was a breach of natural justice. What is a material issue? An issue is material if it is shown to have had the potential to make a significant impact on the overall outcome of the adjudication.

Here, the court held that the adjudicator's job was to address the sum due in the payment cycle. The capping beam claim was put forward as a reduction to the amount which was due in that cycle and as a defence in the adjudication to the sum claimed.  The court held that the adjudicator had jurisdiction to consider it - and should have done so. This was the case despite the capping beam issue not having been mentioned in the relevant Payment Notice.

Some take away points:

  • Parties commencing adjudications, particularly to claim payment, should be mindful that they have their own "house in order" given the risk of wider issues being raised in defence to such claims.
  • Once a "true valuation" of an application is sought, the risk of broader issues being raised is greater. An option to avoid this is to simply seek a declaration on a specific issue rather than claiming a particular sum.
  • While the court usually enforces an adjudicator's decision, this is a reminder that it will not always do so. This risk should be factored into the decision as to whether adjudication is the appropriate method to resolve the dispute in the first place.